==National Railway System==
==National Railway System==
===National Railway Operator===
===National Railway Operator===
Chemins de fer Luxembourgeois ([http://www.cfl.lu CFL]).
Société Nationale des Chemins de fer Luxembourgeois ([https://www.cfl.lu/en-gb CFL]).


==Language==
==Language==
Letzebuergesch, French and German
Luxembourgish (''Letzebuergesch''), French and German


==Currency==
==Currency==
Line 29: Line 29:
===Engineering Information===
===Engineering Information===
[https://www.cfl.lu/en-gb/works Work Sites]
[https://www.cfl.lu/en-gb/works Work Sites]
There is another link for disruptions.
[https://www.cfl.lu/en-gb/disturbances Disruptions]


===Bus Information===
===Bus Information===
[http://www.mobiliteit.lu/horaires-reseaux/transports-publics/bus.php Horaires et réseaux - Bus]
[https://www.mobiliteit.lu/fr/horaires-et-lignes/bus/ Horaires et Lignes - Bus]
 
===Tram Information===
[https://www.mobiliteit.lu/fr/horaires-et-lignes/tram/ Horaires et Ligne - Tram]


==Maps==
==Maps==
===Printed Maps===
===Printed Maps===
*European Railway Atlas: France, Netherlands, Belgium, Luxembourg by M.G. Ball (1991) (ISBN 0-7110-2011-6)
*[[Printed Maps#ERA-E | European Railway Atlas (All-Europe Edition)]] by M.G. Ball.
*[http://www.europeanrailwayatlas.com European Railway Atlas] by M.G. Ball (2008 onwards)
*[[Printed Maps#ERA-R-1  | European Railway Atlas (Regional Atlas Series, Book 1: Norway, Sweden, Finland, Denmark, Great Britain, Ireland, Portugal, Spain, France, Belgium, Netherlands and Luxembourg)]] by M.G. Ball.
*Eisenbahnatlas Frankreich, Band 1 Nord (ISBN 978-3-89494-143-7), published by Verlag Schweers + Wall GmbH ([http://www.schweers-wall.de website] in French, German, English and Italian). Page 19 shows railways in southern half of Luxembourg at 1:300.000 scale. Eisenbahnatlas Deutschland (ISBN 978-3-89494-146-8) by the same publisher, also at 1:300.000 scale, has a page with the Trier - Wasserbillig area. Both atlases have Single and double-track lines distinguished. Tourist lines are identified and named. Lines out of use and those entirely closed are also shown. Rivers, canals and forests are marked.
*[[Printed Maps#SW-FR-1 | Eisenbahnatlas Frankreich Band 1: Nord]] by Schweers + Wall. Page 19 shows railways in southern half of Luxembourg.  
*[[Printed Maps#SW-DE | Eisenbahnatlas Deutschland]] by Schweers + Wall - has a page including the Trier - Wasserbillig area.
*A fourth edition of the [https://nijverepublishers.nl/en/Books-and-maps/Benelux-Rail-Topo Benelux Rail Topo] was published in 2023 (ISBN/EAN 978 90 73280 19 9). In full colour to a scale of 1:550,000 and with a register of over 1,000 stations.


===Web-based Maps===
===Web-based Maps===
*[http://www.sporenplan.nl/ Sporenplan] has a schematic track diagram. Click on "Sporenplannen" on the left hand side for a map showing the countries covered.
*[http://www.sporenplan.nl/ Sporenplan] has a schematic track diagram. Click on "Sporenplannen" on the left hand side for a map showing the countries covered.
*Thorsten Büker's [http://www.bueker.net/trainspotting/maps_benelux.php Benelux Map]. Although this remains on-line, the Büker maps are no longer being maintained. Last updated November 2011.
*Thorsten Büker's [https://websites.umich.edu/~yopopov/rrt/railroadmaps/netherlands_belgium_luxembourg.html Benelux Map].Last updated January 2023


==Ticketing==
==Ticketing==
The [http://www.cfl.lu/espaces/voyageurs/en/billets-et-abonnements/billets-au-luxembourg Tickets in Luxembourg] web page gives details of all ticket types, including the useful ''Dagesbilljee'' (day ticket) and ''Saar-Lor-Lux'' international rover ticket.
Since 29 February 2020, all public transport in Luxembourg has been free of charge to use at all times which includes CFL trains in second class. The [https://www.cfl.lu/en-gb/ticket CFL Tickets] web page gives details of all remaining ticket types including domestic First Class tickets, (and note as at October 2022 that an all-day 1st class day ticket was available for €6).


==Infrastructure==
==Infrastructure==
===Infrastructure Authority===
===Infrastructure Authority===
The Administration des Chemins de Fer ([http://railinfra.lu/ ACF]) is the national authority for the railways.
The Administration des Chemins de Fer ([https://acf.gouvernement.lu/en.html/ ACF]) is the national authority for the railways and tramways.


===Network Statement===
===Network Statement===
[http://railinfra.lu/Document_reference/index.html Documents de référence du réseau] > ''Network Statement DRR 2018 (english version) onwards''
[https://acf.gouvernement.lu/fr/sillon/Document-de-reference-du-reseau.html Documents de Référence du Réseau (DDR)] > Network Statements for DRR 2023 and DDR 2024 (english versions).


===Gauge===
===Gauge===
Line 57: Line 66:


===Electrification===
===Electrification===
All CFL passenger routes are electrified at 25 kV 50 Hz as defined in The Railway Administration (ACF) 2019 Network Statement.
All CFL passenger routes are electrified at 25 kV 50 Hz as defined in The Railway Administration (ACF) 2020 Network Statement.
 
The Luxtram tramway system operates at 750 V dc.


===Rule of the road===
===Rule of the road===
Line 69: Line 80:
   
   
==Tourist Lines==
==Tourist Lines==
*[http://www.train1900.lu/index.php?lang=en L'Association des Musee et Tourisme Ferroviaires (AMTF) ''(Train 1900)''] (standard gauge, 8 km length): Pétange (close to CFL station) to Bois de Rodange with reversal at Fond de Gras. A connection with the CFL network at Pétange sees occasional through excursion trains.
*[https://www.train1900.lu/?lang=en L'Association des Musee et Tourisme Ferroviaires (AMTF) ''(Train 1900)''] (standard gauge, 8 km length): Pétange (close to CFL station) to Bois de Rodange with reversal at Fond de Gras. A connection with the CFL network at Pétange sees occasional through excursion trains.
* [http://minieresbunn.lu/index.php/fr Minièresbunn Doihl asbl (MBD)] (700 mm gauge): a preserved mining line, from Fond de Gras via Doihl and through a 1400 m long tunnel to Lasauvage. Thence are two branches: to Saulnes [France] and to Lasauvage Eglise. Part (including the tunnel) is electrified at 500 V dc while other sections are worked by steam or diesel.
* [https://minieresbunn.lu/fr/ Minièresbunn Doihl asbl (MBD)] (700 mm gauge): a preserved mining line, from Fond de Gras via Doihl and through a 1400 m long tunnel to Lasauvage. Thence are two branches: to Saulnes [France] and to Lasauvage Eglise. Part (including the tunnel) is electrified at 500 V dc while other sections are worked by steam or diesel.
* [http://www.mnm.lu Musée National de Mines de Fer] (700 mm gauge 4.2 km circuit): a preserved mining line at Rumelange.
* [https://www.mnm.lu/ Musée National de Mines de Fer] (700 mm gauge 4.2 km circuit): a preserved mining line at Rumelange.
* [http://www.visit-eislek.lu/en/tour/t/national-slate-museum-haut-martelange Ardoisière Haut-Martelange] (narrow gauge, less than 1 km length); a tourist line next to the national slate museum at Martelange Haut. Trains normally run half hourly in the afternoon of the first Sunday of the month in summer [from May to October].
* [https://www.ardoise.lu/?lang=en Slate Museum Industrial Train Tour] (narrow gauge, less than 1 km length); a tourist line at the national slate museum at Martelange Haut. Trains normally run in the afternoon on Sundays and Holidays in summer subject to weather and availability.


==Metro==
==Metro==
None
None


==Trams==
== Trams/LRT Systems ==
The first section of a new Luxtram tram network opened through Kirchberg on 10 December 2017 between Luxexpo and Rout Bréck–Pafendall (where there is a funicular link to the CFL Pfaffenthal-Kirchberg station). The second section, with catenary-free contactless running, west from Rout Bréck–Pafendall to Stäreplaz/Place de l'Etoile–Pafendall opened on 27 July 2018; further extensions at both ends are under construction (and should see the line extended to Gare Central - the central station by the end of 2020) - see [http://www.luxtram.lu/ Luxtram] (in French or German) or [https://wikimonde.com/article/Tramway_de_Luxembourg Wikimonde] (in French) websites.
Luxtram - see [http://www.luxtram.lu/ Luxtram] (in French or German) or [https://wikimonde.com/article/Tramway_de_Luxembourg Wikimonde] (in French) websites.
 
A track plan for the Luxembourg Luxtram system is available on the [https://www.gleisplanweb.eu/Map-e.php?Map=Luxemburg Gleisplanweb site], and was current at January 2024.
 
Planning has started on a new fast tram line between Luxembourg and Esch-sur-Alzette, with a planned opening date in 2028.
 
==Recent and Future Changes==
 
===Recent ''(latest first)'' changes===
Further extensions of Luxtram at both ends are under construction, with indicated completion dates of mid-2024 for the first part of the extension south to the Cloche d'Or area and the beginning of 2025 for the extension east to Findel airport
 
A 4 metre section of the roof of the 236 metre single track Schieburg tunnel, on Line 10 north from Luxembourg to Gouvy and Liège, collapsed during maintenance work at the end of August 2022, closing it to all traffic.
The reopening was almost a year later on 24 July 2023 after repair and reinforcement of the roof of the tunnel.
 
The fourth section of the new Luxtram tram network, going south between Gare Centrale and Lycée Bouneweg, opened to the public from midday 11 September 2022.


A track plan for the Luxembourg Luxtram system is available on the [http://www.gleisplanweb.eu/ Gleisplanweb site], and was current at the end of July 2018.
As part of the creation of an intermodal hub an additional platform and two further through tracks have been added at Ettelbruck station. This also allows Diekirch branch trains to proceed as far as Ettelbruck to wait for trains off the branch there. This project was completed in 2022.


==Recent ''(latest first)'' and Future Changes==
CFL officially inaugurated two new platforms, four new platform tracks (nos. 11-14) and a new footbridge at Luxembourg Gare Centrale on 12 December 2021.
The new parallel viaduct at Pulvermuhle (just north of Luxembourg), allowing Lines 10 and 30 to be split, and the associated double tracking of the line through to Sandweiler-Contern were inaugurated on 11 June 2019.


A new cross border service, routed via Trier West, is planned at the end of 2019 as part of a Luxembourg - Wasserbillig - Wittlich service on Line 30.
The third section of the new Luxtram tram network, also with catenary-free contactless running, going south between Stäreplaz and Gare Centrale opened on 13 December 2020.  


Conversion of line 5, Luxembourg – Kleinbettingen - frontier, from 3 kV DC to 25 kV 50 Hz ac : was completed in autumn 2018.
All public transport (Second Class only) in Luxembourg became free to use from 29 February 2020 in an effort to ease road congestion. Free Second Class public transport for under 20s started on 1 August 2018.  


On 10 December 2017 new stations opened at Howald (on the Bettembourg line) and at Pfaffenthal-Kirchberg (on the Wasserbillig line, affording connection by funicular with the new tram line (see above)).
The new parallel viaduct at Pulvermühle (just north of Luxembourg Gare Centrale), allowing Lines 10 and 30 to be split, and the associated double tracking of the line through to Sandweiler-Contern were inaugurated on 11 June 2019.
 
A new cross border service, routed via Trier West, was planned at the end of 2019 as part of a Luxembourg - Wasserbillig - Wittlich service on Line 30. However, works to upgrade stations of the Trierer Weststrecke, and provide new ones, have been heavily delayed so the earliest regular passenger service will start is now 2024. An improved service started running on Line 30 in December 2019, but it is routed via Trier Hbf at present.
 
The second section of the new Luxtram tram network, with catenary-free contactless running, west from Rout Bréck–Pafendall to Stäreplaz/Etoile opened on 27 July 2018.
 
Conversion of line 5, Luxembourg – Kleinbettingen - frontier, from 3 kV DC to 25 kV 50 Hz ac was completed in autumn 2018.
 
On 10 December 2017 new stations opened at Howald (on the Bettembourg line) and at Pfaffenthal-Kirchberg (on the Wasserbillig line, affording connection by funicular with the new tram line (see below)).
 
From 20 July 2017 the CFL Luxembourg rail network was equipped with the ETCS level 1 European train control system, See [https://groupe.cfl.lu/en-gb/project/detail/european-train-control-system CFL ETCS Level 1].
 
The first section of the new Luxtram tram network opened through Kirchberg on 10 December 2017 between Luxexpo and Rout Bréck–Pafendall (where there is a funicular link to the CFL Pfaffenthal-Kirchberg station).  


From 4 April 2016 the service from Thionville to Longwy over the Bettembourg avoiding line was withdrawn.  
From 4 April 2016 the service from Thionville to Longwy over the Bettembourg avoiding line was withdrawn.  
Line 95: Line 131:
From 17 February 2016 Rodange - Athus [BE] [ - Virton] was reduced to a skeleton service because the introduction of different signalling systems meant there was no suitable CFL rolling stock available; the service was withdrawn completely from 20 June 2016 but resumed from 11 December 2016. <!--- IF/WHEN THIS GETS DELETED REMEMBER TO DELETE EQUIVALENT BELGIUM ENTRY --->
From 17 February 2016 Rodange - Athus [BE] [ - Virton] was reduced to a skeleton service because the introduction of different signalling systems meant there was no suitable CFL rolling stock available; the service was withdrawn completely from 20 June 2016 but resumed from 11 December 2016. <!--- IF/WHEN THIS GETS DELETED REMEMBER TO DELETE EQUIVALENT BELGIUM ENTRY --->


Double tracking of the line from Hollerich to Petange completed in December 2012.
Double tracking of the line from Hollerich to Pétange completed in December 2012.


The extension of the line across the border from Dudelange to Volmerange-les-Mines in France opened to public traffic on 15 December 2003.
The extension of the line across the border from Dudelange to Volmerange-les-Mines in France opened to public traffic on 15 December 2003.


Work is under way (at December 2018) on the following projects:-
===Future changes===
* Gare Centrale is undergoing a long-term rebuilding programme to increase capacity, started in 2006, including adding two extra platforms and four new tracks. One new track should be opened at the end of 2019 and the rest at the end of 2021 with project completion 2022..
Two further extensions of the Luxtram network were approved in February 2024. A line to the Kirchberg Plateau, Pfaffenthal -
* new line to be built from Howald to Bettembourg. The first phase, covering construction of the new line and temporary connections to the existing line at Howald and Bettembourg, was finally approved in February 2016. Planned for completion in 2024.
Kirchberg station and the new K2 neighbourhood, with first phase open in 2027. The HO line, branching off from near Gare Centrale, to serve the future "Nei Hollerich" neighbourhood and its Hollerich interchange station, with first phase open in 2028.
* two new 'peripherique' stations to be constructed at Dommeldange and Cessange.
 
Work is underway (at December 2023) on the following projects:-
* Gare Centrale is undergoing a long-term rebuilding programme to increase capacity, started in 2006, including adding two extra platforms and four new tracks. One new track (no. 11) was opened at the December 2019 timetable change and the remaining three (nos. 12, 13 & 14) opened on 12 December 2021. Further work remodelling the southern approaches started in 2022. The extension project completion is due in 2025 with gradual commissioning of Luxembourg Station in its new form.
* A new line is to be built from Howald to Bettembourg. The first phase, covering construction of the new line and temporary connections to the existing line at Howald and Bettembourg, was approved in February 2016. It is planned for technical and commercial commissioning to gradually take place from 2027 onwards.
* two new 'peripherique' stations are to be constructed at Dommeldange and Cessange.
 
Planning started in 2020 on a new fast tram line between Luxembourg via Esch-sur-Alzette to Belval and Belvaux, with a planned opening date to Leudelange in 2026. Further sections are planned to open at 2 year intervals; reaching Esch-sur-Alzette by 2032 with Belval and Belvaux being reached in 2035.


All [Second Class] public transport in Luxembourg is to be free from 1st. March 2020 in an effort to ease road congestion.  
See [https://transports.public.lu/fr/mobilite/transport-en-commun/tram/pour-en-savoir-plus-tram-rapide.html Le Tram Rapide] (In French).
Free [Second class] public transport for under 20s started on 1st. August 2018.


Other plans (see [http://www.mt.public.lu/presse/actualite/2007/10/01mobil2020/index.html on-line brochure] (in French) issued in 2007), with no target date, include:
A proposal for SuperBus feeder routes in France could threaten the outer end of Line 60c: Esch-sur-Alzette - Audun le Tiche with closure in 2028.
* double tracking of the line from Rodange to Longwy
* new line from Belval Universite (formerly Belval-Usines) to Belval Mairie
* new tunnel between Belval to Oberkorn
* new line from Hamm (west curve) and Sandweiler (east curve) to Findel Airport and Kirchberg Expo
* modernisation of the Dommeldange to Ettelbruck line
* double tracking and a new platform to be built at Michelau
* Bettembourg - Thionville to be quadrupled


==Special Notes==
==Special Notes==
Line 121: Line 155:
==See also==
==See also==
{{Navbox Luxembourg}}
{{Navbox Luxembourg}}
[[Category:General Information]]

Latest revision as of 19:38, 18 February 2024

Country Name

Luxembourg

National Railway System

National Railway Operator

Société Nationale des Chemins de fer Luxembourgeois (CFL).

Language

Luxembourgish (Letzebuergesch), French and German

Currency

Euro

UIC code

numeric 82; alpha L

Timetable

Journey Planner

Liaisons - recherche

Downloadable Timetable

Pocket Timetables. Under "Pocket timetables", select the option required:

  • National
  • International

Printed Timetable

CFL no longer produces a printed timetable. However, timetable leaflets are available for each line and for bus services and international trains.

Engineering Information

Work Sites

There is another link for disruptions.

Disruptions

Bus Information

Horaires et Lignes - Bus

Tram Information

Horaires et Ligne - Tram

Maps

Printed Maps

Web-based Maps

  • Sporenplan has a schematic track diagram. Click on "Sporenplannen" on the left hand side for a map showing the countries covered.
  • Thorsten Büker's Benelux Map.Last updated January 2023

Ticketing

Since 29 February 2020, all public transport in Luxembourg has been free of charge to use at all times which includes CFL trains in second class. The CFL Tickets web page gives details of all remaining ticket types including domestic First Class tickets, (and note as at October 2022 that an all-day 1st class day ticket was available for €6).

Infrastructure

Infrastructure Authority

The Administration des Chemins de Fer (ACF) is the national authority for the railways and tramways.

Network Statement

Documents de Référence du Réseau (DDR) > Network Statements for DRR 2023 and DDR 2024 (english versions).

Gauge

Standard

Electrification

All CFL passenger routes are electrified at 25 kV 50 Hz as defined in The Railway Administration (ACF) 2020 Network Statement.

The Luxtram tramway system operates at 750 V dc.

Rule of the road

Right (except for the Sterpenich - Luxembourg section which is used by SNCB and has left hand running).

Distances

Detailed distances for each line are given in the Network Statement Appendix 2A: The Luxembourg Rail Network

Other Railways

None.

Tourist Lines

  • L'Association des Musee et Tourisme Ferroviaires (AMTF) (Train 1900) (standard gauge, 8 km length): Pétange (close to CFL station) to Bois de Rodange with reversal at Fond de Gras. A connection with the CFL network at Pétange sees occasional through excursion trains.
  • Minièresbunn Doihl asbl (MBD) (700 mm gauge): a preserved mining line, from Fond de Gras via Doihl and through a 1400 m long tunnel to Lasauvage. Thence are two branches: to Saulnes [France] and to Lasauvage Eglise. Part (including the tunnel) is electrified at 500 V dc while other sections are worked by steam or diesel.
  • Musée National de Mines de Fer (700 mm gauge 4.2 km circuit): a preserved mining line at Rumelange.
  • Slate Museum Industrial Train Tour (narrow gauge, less than 1 km length); a tourist line at the national slate museum at Martelange Haut. Trains normally run in the afternoon on Sundays and Holidays in summer subject to weather and availability.

Metro

None

Trams/LRT Systems

Luxtram - see Luxtram (in French or German) or Wikimonde (in French) websites.

A track plan for the Luxembourg Luxtram system is available on the Gleisplanweb site, and was current at January 2024.

Planning has started on a new fast tram line between Luxembourg and Esch-sur-Alzette, with a planned opening date in 2028.

Recent and Future Changes

Recent (latest first) changes

Further extensions of Luxtram at both ends are under construction, with indicated completion dates of mid-2024 for the first part of the extension south to the Cloche d'Or area and the beginning of 2025 for the extension east to Findel airport

A 4 metre section of the roof of the 236 metre single track Schieburg tunnel, on Line 10 north from Luxembourg to Gouvy and Liège, collapsed during maintenance work at the end of August 2022, closing it to all traffic. The reopening was almost a year later on 24 July 2023 after repair and reinforcement of the roof of the tunnel.

The fourth section of the new Luxtram tram network, going south between Gare Centrale and Lycée Bouneweg, opened to the public from midday 11 September 2022.

As part of the creation of an intermodal hub an additional platform and two further through tracks have been added at Ettelbruck station. This also allows Diekirch branch trains to proceed as far as Ettelbruck to wait for trains off the branch there. This project was completed in 2022.

CFL officially inaugurated two new platforms, four new platform tracks (nos. 11-14) and a new footbridge at Luxembourg Gare Centrale on 12 December 2021.

The third section of the new Luxtram tram network, also with catenary-free contactless running, going south between Stäreplaz and Gare Centrale opened on 13 December 2020.

All public transport (Second Class only) in Luxembourg became free to use from 29 February 2020 in an effort to ease road congestion. Free Second Class public transport for under 20s started on 1 August 2018.

The new parallel viaduct at Pulvermühle (just north of Luxembourg Gare Centrale), allowing Lines 10 and 30 to be split, and the associated double tracking of the line through to Sandweiler-Contern were inaugurated on 11 June 2019.

A new cross border service, routed via Trier West, was planned at the end of 2019 as part of a Luxembourg - Wasserbillig - Wittlich service on Line 30. However, works to upgrade stations of the Trierer Weststrecke, and provide new ones, have been heavily delayed so the earliest regular passenger service will start is now 2024. An improved service started running on Line 30 in December 2019, but it is routed via Trier Hbf at present.

The second section of the new Luxtram tram network, with catenary-free contactless running, west from Rout Bréck–Pafendall to Stäreplaz/Etoile opened on 27 July 2018.

Conversion of line 5, Luxembourg – Kleinbettingen - frontier, from 3 kV DC to 25 kV 50 Hz ac was completed in autumn 2018.

On 10 December 2017 new stations opened at Howald (on the Bettembourg line) and at Pfaffenthal-Kirchberg (on the Wasserbillig line, affording connection by funicular with the new tram line (see below)).

From 20 July 2017 the CFL Luxembourg rail network was equipped with the ETCS level 1 European train control system, See CFL ETCS Level 1.

The first section of the new Luxtram tram network opened through Kirchberg on 10 December 2017 between Luxexpo and Rout Bréck–Pafendall (where there is a funicular link to the CFL Pfaffenthal-Kirchberg station).

From 4 April 2016 the service from Thionville to Longwy over the Bettembourg avoiding line was withdrawn.

From 17 February 2016 Rodange - Athus [BE] [ - Virton] was reduced to a skeleton service because the introduction of different signalling systems meant there was no suitable CFL rolling stock available; the service was withdrawn completely from 20 June 2016 but resumed from 11 December 2016.

Double tracking of the line from Hollerich to Pétange completed in December 2012.

The extension of the line across the border from Dudelange to Volmerange-les-Mines in France opened to public traffic on 15 December 2003.

Future changes

Two further extensions of the Luxtram network were approved in February 2024. A line to the Kirchberg Plateau, Pfaffenthal - Kirchberg station and the new K2 neighbourhood, with first phase open in 2027. The HO line, branching off from near Gare Centrale, to serve the future "Nei Hollerich" neighbourhood and its Hollerich interchange station, with first phase open in 2028.

Work is underway (at December 2023) on the following projects:-

  • Gare Centrale is undergoing a long-term rebuilding programme to increase capacity, started in 2006, including adding two extra platforms and four new tracks. One new track (no. 11) was opened at the December 2019 timetable change and the remaining three (nos. 12, 13 & 14) opened on 12 December 2021. Further work remodelling the southern approaches started in 2022. The extension project completion is due in 2025 with gradual commissioning of Luxembourg Station in its new form.
  • A new line is to be built from Howald to Bettembourg. The first phase, covering construction of the new line and temporary connections to the existing line at Howald and Bettembourg, was approved in February 2016. It is planned for technical and commercial commissioning to gradually take place from 2027 onwards.
  • two new 'peripherique' stations are to be constructed at Dommeldange and Cessange.

Planning started in 2020 on a new fast tram line between Luxembourg via Esch-sur-Alzette to Belval and Belvaux, with a planned opening date to Leudelange in 2026. Further sections are planned to open at 2 year intervals; reaching Esch-sur-Alzette by 2032 with Belval and Belvaux being reached in 2035.

See Le Tram Rapide (In French).

A proposal for SuperBus feeder routes in France could threaten the outer end of Line 60c: Esch-sur-Alzette - Audun le Tiche with closure in 2028.

Special Notes

CFL provides the only passenger service to Audun-le-Tiche and Volmerange les Mines (France).

See also